Axminster 132kV: grid connection queue

Axminster 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

4 projects with 590 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2024 to 23 Jun 2038.

4projects in the queue
590 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
150 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
AxminsterHB825AXM LTDBattery storage12031 Oct 2024n/aAwaiting Consents1
Axminster BESSCSE25 LIMITEDBattery storage15031 Oct 2028High31 Oct 2030Scoping1
Axminster - New ConnectionENSO GREEN HOLDINGS B LIMITEDBattery storage12030 Jun 2029Medium30 Jun 2029Scoping1
Old Park FarmSTARLIGHT ENERGY UK LIMITEDSolar + storage20023 Jun 2038Low23 Jun 2038Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
27 Oct 2026Old Park Farm31 Oct 203823 Jun 2038-4 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Axminster GSPSSEN Distribution5.0 km

Thinking of connecting near Axminster 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points