Axminster 132kV: grid connection queue
Axminster 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 590 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2024 to 23 Jun 2038.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Axminster | HB825AXM LTD | Battery storage | 120 | 31 Oct 2024 | n/a | Awaiting Consents | 1 | |
| Axminster BESS | CSE25 LIMITED | Battery storage | 150 | 31 Oct 2028 | High | 31 Oct 2030 | Scoping | 1 |
| Axminster - New Connection | ENSO GREEN HOLDINGS B LIMITED | Battery storage | 120 | 30 Jun 2029 | Medium | 30 Jun 2029 | Scoping | 1 |
| Old Park Farm | STARLIGHT ENERGY UK LIMITED | Solar + storage | 200 | 23 Jun 2038 | Low | 23 Jun 2038 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 27 Oct 2026 | Old Park Farm | 31 Oct 2038 | 23 Jun 2038 | -4 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Axminster GSP | SSEN Distribution | 5.0 km |
Thinking of connecting near Axminster 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Axminster 400kV: 50 MW waiting
- Gravity 400kV: 500 MW waiting
- West Country Connection Node D 400kV: 700 MW waiting
- Chickerell 400kV: 3,450 MW waiting
- Chickerell B 400kV: 480 MW waiting