Benzene

Gravity 400kV: grid connection queue

Gravity 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 500 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.

1project in the queue
500 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Somerset Energy ParkLow Carbon Solar Park 35 LimitedSolar + storage50031 Oct 2037Low31 Oct 2037Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Larkhill PrimarySSEN Distribution19.0 km0 MW12 MW

Thinking of connecting near Gravity 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points