West Country Connection Node D 400kV: grid connection queue

West Country Connection Node D 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 700 MW are waiting to connect here (largest by capacity: mixed and other, battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.

2projects in the queue
700 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Wick Moor DroveBSR APPLICATIONS LIMITEDMixed and other50031 Oct 2037Low31 Oct 2037Scoping1
Shurton BESSField Shurton LtdBattery storage20031 Oct 2037Low31 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Chilton Cantello PrimarySSEN Distribution16.4 km0 MW7.2 MW
Larkhill PrimarySSEN Distribution16.9 km0 MW12 MW
Sparkford PrimarySSEN Distribution17.1 km0 MW2.2 MW
West Hendford PrimarySSEN Distribution18.8 km0 MW17 MW
Yeovil BSPSSEN Distribution19.3 km0 MW17 MW
Yeovil PrimarySSEN Distribution19.4 km0 MW5.9 MW

Thinking of connecting near West Country Connection Node D 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.