West Country Connection Node D 400kV: grid connection queue
West Country Connection Node D 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 700 MW are waiting to connect here (largest by capacity: mixed and other, battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Wick Moor Drove | BSR APPLICATIONS LIMITED | Mixed and other | 500 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| Shurton BESS | Field Shurton Ltd | Battery storage | 200 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Chilton Cantello Primary | SSEN Distribution | 16.4 km | 0 MW | 7.2 MW |
| Larkhill Primary | SSEN Distribution | 16.9 km | 0 MW | 12 MW |
| Sparkford Primary | SSEN Distribution | 17.1 km | 0 MW | 2.2 MW |
| West Hendford Primary | SSEN Distribution | 18.8 km | 0 MW | 17 MW |
| Yeovil BSP | SSEN Distribution | 19.3 km | 0 MW | 17 MW |
| Yeovil Primary | SSEN Distribution | 19.4 km | 0 MW | 5.9 MW |
Thinking of connecting near West Country Connection Node D 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Bridgewater 400kV: 57 MW waiting
- West Country Connection Node E 400kV: 480 MW waiting
- Gravity 400kV: 500 MW waiting
- Bridgwater 400/132kV: 57 MW waiting
- West Country Connection Node A 400kV: 300 MW waiting