Bridgwater 400/132kV: grid connection queue
Bridgwater 400/132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 57 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Aug 2028 to 31 Aug 2028.
1project in the queue
57 MWwaiting to connect
6 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
57 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Bridgwater (tertiary) | ENSO GREEN HOLDINGS H LIMITED | Solar + storage | 57 | 31 Aug 2028 | High | 31 Aug 2030 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Bridgwater 400/132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Woolavington 400kV: 1,630 MW waiting
- Bridgewater 400kV: 57 MW waiting
- West Country Connection Node A 400kV: 300 MW waiting
- Shurton 400kV: 3,340 MW waiting
- Gravity 400kV: 500 MW waiting