Woolavington 400kV: grid connection queue
Woolavington 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 1,630 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2030 to 31 Oct 2037.
3projects in the queue
1,630 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Icewind Hinkley Point | KARI ENERGY LIMITED | Battery storage | 1,000 | 31 Oct 2030 | Medium | 31 Oct 2030 | Scoping | 1 |
| Noventum- Bridgwater | NOVENTUM POWER SOLAR 13 LIMITED | Battery storage | 380 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| Bridgwater Energy Park | EXAGEN GROUP LIMITED | Battery storage | 250 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Woolavington 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- West Country Connection Node A 400kV: 300 MW waiting
- Bridgwater 400/132kV: 57 MW waiting
- Bridgewater 400kV: 57 MW waiting
- West Country Connection Node E 400kV: 480 MW waiting
- Shurton 400kV: 3,340 MW waiting