Shurton 400kV: grid connection queue
Shurton 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 3,340 MW is waiting to connect here (largest by capacity: nuclear). Contracted dates run from 31 Mar 2029 to 31 Mar 2029.
1project in the queue
3,340 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Hinkley Point C | NNB GENERATION COMPANY (HPC) LIMITED | Nuclear | 3,340 | 31 Mar 2029 | Medium | 31 Mar 2029 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Shurton 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Bridgwater 400/132kV: 57 MW waiting
- Woolavington 400kV: 1,630 MW waiting
- West Country Connection Node A 400kV: 300 MW waiting
- Bridgewater 400kV: 57 MW waiting
- Taunton 400kV: 100 MW waiting