Chickerell 400kV: grid connection queue
Chickerell 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 3,450 MW are waiting to connect here (largest by capacity: offshore wind, battery storage). Contracted dates run from 31 Oct 2028 to 6 Dec 2036.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Chickerell Solar PV & BESS | CHICKERELL STORAGE LIMITED | Battery storage | 400 | 31 Oct 2028 | High | 31 Oct 2030 | Consents Approved | 2 |
| BESS North Farm | REWE 5 LIMITED | Battery storage | 150 | 1 Nov 2031 | Medium | 1 Nov 2031 | Scoping | 1 |
| Portwind | SE PORTWIND LTD | Offshore wind | 2,500 | 6 Dec 2036 | Low | 6 Dec 2036 | Scoping | 1 |
| Chickerell | ENSO GREEN HOLDINGS X LIMITED | Solar + storage | 400 | 6 Dec 2036 | Low | 6 Dec 2036 | Awaiting Consents | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Charminster Primary | SSEN Distribution | 2.5 km | 0 MW | 4.9 MW |
| Dorchester Primary | SSEN Distribution | 3.9 km | 0 MW | 19 MW |
| Maiden Newton Primary | SSEN Distribution | 8.8 km | 0 MW | 5.8 MW |
| Redlands Primary | SSEN Distribution | 9.4 km | 0 MW | 3.8 MW |
| Puddletown Primary | SSEN Distribution | 9.5 km | 0 MW | 5.8 MW |
| Cerne Abbas Primary | SSEN Distribution | 9.5 km | 0 MW | 2 MW |
Thinking of connecting near Chickerell 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Chickerell B 400kV: 480 MW waiting
- Axminster 132kV: 590 MW waiting
- Axminster 400kV: 50 MW waiting
- Shaftesbury 132kV: 100 MW waiting
- Mannington 400kV: 142 MW waiting