Mannington 400kV: grid connection queue
Mannington 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
3 projects with 142 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 30 Oct 2025 to 28 Apr 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Mannington Tertiary | MANNINGTON ENERGY CENTRE LIMITED | Battery storage | 48 | 30 Oct 2025 | n/a | Consents Approved | none | |
| Mannington | PIVOTED POWER LLP | Solar + storage | 48 | 30 Nov 2025 | n/a | Consents Approved | none | |
| Mannington | BAYWA R.E. UK LIMITED | Solar + storage | 48 | 28 Apr 2028 | High | 28 Apr 2030 | Scoping | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 11 Aug 2026 | Mannington | 30 Aug 2030 | 28 Apr 2028 | -28 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Gussage St Michael Primary | SSEN Distribution | 2.3 km | 0 MW | 7.2 MW |
| Wimborne St Giles Primary | SSEN Distribution | 2.5 km | 0 MW | 0.5 MW |
| Hinton Martell Primary | SSEN Distribution | 5.2 km | 0 MW | 6.3 MW |
| Minchington Primary | SSEN Distribution | 5.8 km | 0 MW | 3.3 MW |
| Verwood Primary | SSEN Distribution | 6.8 km | 0 MW | 3.5 MW |
| Tarrant Rushton Primary | SSEN Distribution | 7.5 km | 0 MW | 3.5 MW |
Thinking of connecting near Mannington 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Shaftesbury 132kV: 100 MW waiting
- Marchwood 400kV: 200 MW waiting
- Nursling 400kV: 2,980 MW waiting
- Chickerell 400kV: 3,450 MW waiting
- Chickerell B 400kV: 480 MW waiting