Marchwood 400kV: grid connection queue

Marchwood 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 1 Jun 2028 to 1 Jun 2028.

1project in the queue
200 MWwaiting to connect
920 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
200 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
MARCHWOOD ENERGY STORAGEBW ESS DEVELOPMENT UK LIMITEDBattery storage2001 Jun 2028High1 Jun 2030Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Marchwood PrimarySSEN Distribution0.5 km0 MW11 MW
Southampton (Main) BSPSSEN Distribution2.0 km0 MW40 MW
Southampton (Reserve) BSPSSEN Distribution2.0 km0 MW0 MW
Regents Park PrimarySSEN Distribution2.0 km0 MW14 MW
Western Esplanade PrimarySSEN Distribution2.1 km0 MW30 MW
Shirley PrimarySSEN Distribution2.7 km0 MW9.4 MW

Thinking of connecting near Marchwood 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points