Fawley 132kV: grid connection queue
Fawley 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
4 projects with 450 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 24 Oct 2036 to 24 Oct 2036.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Copper Nose BESS | Copper Nose Energy Ltd | Battery storage | 150 | 24 Oct 2036 | Low | 24 Oct 2036 | Scoping | 1 |
| KXP Alpha One | KXP ALPHA I LIMITED | Battery storage | 100 | 24 Oct 2036 | Low | 24 Oct 2036 | Scoping | 1 |
| KXP Alpha Three | KXP ALPHA III LIMITED | Battery storage | 100 | 24 Oct 2036 | Low | 24 Oct 2036 | Scoping | 1 |
| KXP Alpha Two | KXP ALPHA II LIMITED | Battery storage | 100 | 24 Oct 2036 | Low | 24 Oct 2036 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Newport Primary | SSEN Distribution | 3.0 km | 0 MW | 0 MW |
| Cowes BSP | SSEN Distribution | 4.9 km | 0 MW | 0 MW |
| Cowes Primary | SSEN Distribution | 5.0 km | 0 MW | 0 MW |
| Wootton Common BSP | SSEN Distribution | 5.6 km | 0 MW | 0 MW |
| Shalfleet Primary | SSEN Distribution | 6.7 km | 0 MW | 0 MW |
| Binstead Primary | SSEN Distribution | 9.2 km | 0 MW | 0 MW |
Thinking of connecting near Fawley 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Solent Connection Node A 132kV: 100 MW waiting
- Solent Connection Node C 400kV: 2,400 MW waiting
- Marchwood 400kV: 200 MW waiting
- Solent Connection Node B 132kV: 120 MW waiting
- Nursling 400kV: 2,980 MW waiting