Solent Connection Node B 132kV: grid connection queue
Solent Connection Node B 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 120 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2037 to 30 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Pigeon House BESS | Voltwise Power Holdings Limited | Battery storage | 120 | 30 Oct 2037 | Low | 30 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Townhill Park Primary | SSEN Distribution | 0.5 km | 0 MW | 7.5 MW |
| Bitterne Primary | SSEN Distribution | 1.2 km | 0 MW | 3.4 MW |
| Woodmill Lane Primary | SSEN Distribution | 1.9 km | 0 MW | 13 MW |
| Bevois Valley Primary | SSEN Distribution | 2.8 km | 0 MW | 0 MW |
| Woolston Primary | SSEN Distribution | 3.3 km | 0 MW | 7.5 MW |
| Netley Common BSP | SSEN Distribution | 3.3 km | 0 MW | 7.5 MW |
Thinking of connecting near Solent Connection Node B 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Marchwood 400kV: 200 MW waiting
- Solent Connection Node C 400kV: 2,400 MW waiting
- Nursling 400kV: 2,980 MW waiting
- Solent Connection Node A 132kV: 100 MW waiting
- Fawley 132kV: 450 MW waiting