Solent Connection Node C 400kV: grid connection queue
Solent Connection Node C 400kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 2,400 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2038 to 31 Oct 2038.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Bute Hydrogen Project 7.1 | HALDANE ENERGY PROJECT 7 LIMITED | Battery storage | 2,400 | 31 Oct 2038 | Low | 31 Oct 2038 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Bute Hydrogen Project 7.1 | 30 Oct 2031 | 31 Oct 2038 | +84 months |
| 13 Oct 2026 | Bute Hydrogen Project 7.1 | 31 Oct 2038 | 30 Oct 2031 | -84 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Botley Wood GSP | SSEN Distribution | 0.8 km | ||
| Botley Wood BSP | SSEN Distribution | 0.8 km | 0 MW | 72 MW |
| Whitely Primary | SSEN Distribution | 1.9 km | 0 MW | 0.4 MW |
| North Fareham Primary | SSEN Distribution | 2.5 km | 0 MW | 0 MW |
| Plessey Titchfield Primary | SSEN Distribution | 2.7 km | 0 MW | 0 MW |
| Park Gate Primary | SSEN Distribution | 3.5 km | 0 MW | 17 MW |
Thinking of connecting near Solent Connection Node C 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Solent Connection Node A 132kV: 100 MW waiting
- Solent Connection Node B 132kV: 120 MW waiting
- Marchwood 400kV: 200 MW waiting
- Fawley 132kV: 450 MW waiting
- Nursling 400kV: 2,980 MW waiting