Killingholme 400kV: grid connection queue
Killingholme 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 1,040 MW are waiting to connect here (largest by capacity: gas and thermal, solar + storage). Contracted dates run from 30 Sep 2030 to 31 May 2033.
2projects in the queue
1,040 MWwaiting to connect
619 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| North Killingholme Power Project | Uniper UK Limited | Gas and thermal | 540 | 30 Sep 2030 | Medium | 30 Sep 2030 | Consents Approved | none |
| THE CLEAN FUTURE | THE CLEAN FUTURE RENEWABLES LIMITED | Solar + storage | 500 | 31 May 2033 | Low | 31 May 2033 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Thinking of connecting near Killingholme 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- South Humber Connection Node A: 800 MW waiting
- SOUTH HUMBER CONNECTION NODE A 132kV: 240 MW waiting
- Grimsby West 400kV: 6,555 MW waiting
- Grimsby West: 180 MW waiting
- Grimsby West 132kV: 150 MW waiting