Grimsby West 400kV: grid connection queue
Grimsby West 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
7 projects with 6,555 MW are waiting to connect here (largest by capacity: gas and thermal, solar + storage). Contracted dates run from 30 Oct 2033 to 30 Oct 2035.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| EcoGrimsbyWest | Econergy International Limited | Solar + storage | 249 | 30 Oct 2033 | Low | 30 Oct 2033 | Scoping | none |
| Carbon Free 2030 | CARBON FREE 2030 ENERGY LIMITED | Solar + storage | 500 | 30 Jun 2034 | Low | 30 Jun 2034 | Scoping | none |
| Stallingborough PV & BESS Station | STALLINGBOROUGH ENERGY PROJECT LIMITED | Solar + storage | 500 | 30 Oct 2034 | Low | 30 Oct 2034 | Scoping | none |
| Grimsby BESS | Shama BESS Limited | Battery storage | 500 | 30 Apr 2035 | Low | 30 Apr 2035 | Scoping | 1 |
| STALLINGBOROUGH CARBON CAPTURE CCGT | RWE Generation UK Plc | Gas and thermal | 906 | 30 May 2035 | Low | 30 May 2035 | Scoping | none |
| Bute Hydrogen Project 3 | HALDANE ENERGY PROJECT 3 LIMITED | Gas and thermal | 3,600 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
| Great Coates BESS | BRUTON ONE BESS LIMITED | Battery storage | 300 | 30 Oct 2035 | Low | 30 Oct 2035 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 5 times: 3 later and 2 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 3 Nov 2026 | Great Coates BESS | 31 Oct 2031 | 30 Oct 2035 | +48 months |
| 20 Oct 2026 | Grimsby BESS | 30 Oct 2035 | 30 Apr 2035 | -6 months |
| 20 Oct 2026 | Great Coates BESS | 30 Oct 2035 | 31 Oct 2031 | -48 months |
| 13 Oct 2026 | Grimsby BESS | 30 Apr 2035 | 30 Oct 2035 | +6 months |
| 13 Oct 2026 | Great Coates BESS | 31 Oct 2033 | 30 Oct 2035 | +24 months |
Thinking of connecting near Grimsby West 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Grimsby West: 180 MW waiting
- Grimsby West 132kV: 150 MW waiting
- Humber Refinery 400kV: 349 MW waiting
- South Humber Bank 400kV: 118 MW waiting
- South Humber Connection Node A: 800 MW waiting