Humber Refinery 400kV: grid connection queue
Humber Refinery 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 349 MW are waiting to connect here (largest by capacity: gas and thermal, mixed and other). Contracted dates run from 16 Jan 2026 to 31 Oct 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| VPI Immingham B OCGT | VPI IMMINGHAM B LIMITED | Gas and thermal | 299 | 16 Jan 2026 | n/a | Scoping | none | |
| Immingham | VPI IMMINGHAM LLP | Mixed and other | 50 | 31 Oct 2028 | High | 15 Jun 2031 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | Immingham | 1 Jul 2027 | 31 Oct 2028 | +16 months |
Thinking of connecting near Humber Refinery 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- South Humber Bank 400kV: 118 MW waiting
- Grimsby West 400kV: 6,555 MW waiting
- Grimsby West: 180 MW waiting
- Grimsby West 132kV: 150 MW waiting
- Killingholme 400kV: 1,040 MW waiting