Iver 275kV: grid connection queue
Iver 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 50 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 29 Oct 2027 to 29 Oct 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Iver | Juniper Energy Limited | Battery storage | 50 | 29 Oct 2027 | High | 28 Oct 2029 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Sutton Lane Primary | SSEN Distribution | 2.1 km | 22 MW | 0 MW |
| Longford BSP | SSEN Distribution | 2.3 km | 48 MW | 0 MW |
| Yiewsley Primary | SSEN Distribution | 2.4 km | 66 MW | 19 MW |
| Bath Road West Primary | SSEN Distribution | 2.7 km | 22 MW | 0 MW |
| Upton BSP | SSEN Distribution | 3.4 km | 60 MW | 0 MW |
| Upton Primary | SSEN Distribution | 3.4 km | 28 MW | 0 MW |
Thinking of connecting near Iver 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Slough East 132kV: 200 MW waiting
- Laleham GSP (SEPD): 200 MW waiting
- Laleham 132kV: 90 MW waiting
- London West Connection Node A 400kV: 200 MW waiting
- London North West Connection Node A 132kV: 200 MW waiting