Iver 275kV: grid connection queue

Iver 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 50 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 29 Oct 2027 to 29 Oct 2027.

1project in the queue
50 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
50 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
IverJuniper Energy LimitedBattery storage5029 Oct 2027High28 Oct 2029Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Sutton Lane PrimarySSEN Distribution2.1 km22 MW0 MW
Longford BSPSSEN Distribution2.3 km48 MW0 MW
Yiewsley PrimarySSEN Distribution2.4 km66 MW19 MW
Bath Road West PrimarySSEN Distribution2.7 km22 MW0 MW
Upton BSPSSEN Distribution3.4 km60 MW0 MW
Upton PrimarySSEN Distribution3.4 km28 MW0 MW

Thinking of connecting near Iver 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points