Slough East 132kV: grid connection queue
Slough East 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Apr 2038 to 30 Apr 2038.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Laleham BESS | Acorn Power Limited | Battery storage | 200 | 30 Apr 2038 | Low | 30 Apr 2038 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Chalvey BSP | SSEN Distribution | 1.0 km | 88 MW | 0 MW |
| Chalvey Primary | SSEN Distribution | 1.0 km | 84 MW | 0 MW |
| Cippenham BSP | SSEN Distribution | 1.0 km | 96 MW | 0 MW |
| Petersfield Avenue Primary | SSEN Distribution | 1.0 km | 53 MW | 0 MW |
| Slough BSP | SSEN Distribution | 2.1 km | 126 MW | 0 MW |
| Farnham Royal Primary | SSEN Distribution | 3.0 km | 40 MW | 0 MW |
Thinking of connecting near Slough East 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Iver 275kV: 50 MW waiting
- Laleham GSP (SEPD): 200 MW waiting
- Laleham 132kV: 90 MW waiting
- London West Connection Node A 400kV: 200 MW waiting
- London North West Connection Node A 132kV: 200 MW waiting