Slough East 132kV: grid connection queue

Slough East 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Apr 2038 to 30 Apr 2038.

1project in the queue
200 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Laleham BESSAcorn Power LimitedBattery storage20030 Apr 2038Low30 Apr 2038Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Chalvey BSPSSEN Distribution1.0 km88 MW0 MW
Chalvey PrimarySSEN Distribution1.0 km84 MW0 MW
Cippenham BSPSSEN Distribution1.0 km96 MW0 MW
Petersfield Avenue PrimarySSEN Distribution1.0 km53 MW0 MW
Slough BSPSSEN Distribution2.1 km126 MW0 MW
Farnham Royal PrimarySSEN Distribution3.0 km40 MW0 MW

Thinking of connecting near Slough East 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.