Laleham 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 90 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 May 2028 to 30 May 2028.

1project in the queue
90 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
90 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
LalehamJuniper Energy LimitedBattery storage9030 May 2028High30 May 2030Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Sidney Road PrimarySSEN Distribution0.4 km0 MW8.7 MW
East Bedfont PrimarySSEN Distribution0.9 km0 MW0 MW
Causeway PrimarySSEN Distribution1.4 km0 MW25 MW
Stanwell PrimarySSEN Distribution2.3 km0 MW3.8 MW
Laleham GSPSSEN Distribution2.5 km
Church Road PrimarySSEN Distribution2.7 km0 MW0 MW

Thinking of connecting near Laleham 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points