Chessington 132kV: grid connection queue
Chessington 132kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 240 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 16 Nov 2037 to 16 Nov 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Chessington Estate | Chessington BESS Ltd | Battery storage | 240 | 16 Nov 2037 | Low | 16 Nov 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Esher 11kV | UK Power Networks | 1.7 km | 51 MW | 14 MW |
| Surbiton 11kV | UK Power Networks | 2.7 km | 18 MW | 2.1 MW |
| Chessington Grid 33kV | UK Power Networks | 2.8 km | 217 MW | 102 MW |
| Berrylands 11kV | UK Power Networks | 3.8 km | 13 MW | 7.1 MW |
| North Chessington 11kV | UK Power Networks | 3.9 km | 19 MW | 4.1 MW |
| Molesey 11kV | UK Power Networks | 4.3 km | 25 MW | 5.6 MW |
Thinking of connecting near Chessington 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- London North West Connection Node B 400kV: 1,000 MW waiting
- Laleham GSP (SEPD): 200 MW waiting
- Laleham 132kV: 90 MW waiting
- West Weybridge 275kV: 57 MW waiting
- West London Connection Node B 132kV substation: 360 MW waiting