West Weybridge 275kV: grid connection queue
West Weybridge 275kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 57 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Sep 2028 to 30 Sep 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| West Weybridge | EL (WEST WEYBRIDGE) LIMITED | Battery storage | 57 | 30 Sep 2028 | High | 30 Sep 2030 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 6 Oct 2026 | West Weybridge | 31 Oct 2027 | 30 Sep 2028 | +11 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Effingham 11kV | UK Power Networks | 3.5 km | 24 MW | 7.7 MW |
| Byfleet Grid 33kV | UK Power Networks | 6.2 km | 111 MW | 30 MW |
| Cobham Surrey 11kV | UK Power Networks | 7.1 km | 26 MW | 4.8 MW |
| Old Woking 11kV | UK Power Networks | 7.1 km | 23 MW | 3.7 MW |
| Merrow 11kV | UK Power Networks | 7.4 km | 26 MW | 6.7 MW |
| Byfleet 11kV | UK Power Networks | 7.6 km | 40 MW | 13 MW |
Thinking of connecting near West Weybridge 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Chessington 132kV: 240 MW waiting
- Laleham GSP (SEPD): 200 MW waiting
- Laleham 132kV: 90 MW waiting
- London North West Connection Node B 400kV: 1,000 MW waiting
- Iver 275kV: 50 MW waiting