New Dounreay 400kV substation: grid connection queue
New Dounreay 400kV substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 1,700 MW are waiting to connect here (largest by capacity: offshore wind, battery storage). Contracted dates run from 30 Oct 2033 to 31 Oct 2034.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Havbredey | HAVBREDEY LIMITED | Offshore wind | 1,500 | 30 Oct 2033 | Low | 30 Oct 2033 | Scoping | 1 |
| Dounreay BESS | FIELD DEVCO LTD | Battery storage | 200 | 31 Oct 2034 | Low | 31 Oct 2034 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Bettyhill Primary | SSEN Distribution | 15.5 km | 0 MW | 2.1 MW |
| Coldbackie Primary | SSEN Distribution | 18.1 km | 0 MW | 1.8 MW |
Thinking of connecting near New Dounreay 400kV substation?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- DOUNREAY 2 275 kV SUBSTATION: 500 MW waiting
- Dounreay 2 275/33kV GSP: 43 MW waiting
- Strathy Wood 132/33kV: 64 MW waiting
- Connagill 132kV: 99 MW waiting
- Melvich Community Wind Farm 132/33kV: 58 MW waiting