Strathy Wood 132/33kV: grid connection queue
Strathy Wood 132/33kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 64 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Dec 2029 to 31 Dec 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Strathy Wood Wind Farm | RWE Renewables UK Onshore Wind Limited | Onshore wind | 64 | 31 Dec 2029 | High | 17 Nov 2031 | Consents Approved | 2 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Melvich Primary | SSEN Distribution | 10.8 km | 0 MW | 1.7 MW |
| Bettyhill Primary | SSEN Distribution | 12.9 km | 0 MW | 2.1 MW |
| Dounreay GSP | SSEN Distribution | 19.4 km |
Thinking of connecting near Strathy Wood 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Melvich Community Wind Farm 132/33kV: 58 MW waiting
- New Dounreay 400kV substation: 1,700 MW waiting
- DOUNREAY 2 275 kV SUBSTATION: 500 MW waiting
- Dounreay 2 275/33kV GSP: 43 MW waiting
- Connagill 132kV: 99 MW waiting