Benzene

Richborough: grid connection queue

Richborough GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 50 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2025 to 31 Oct 2025.

1project in the queue
50 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Harrington Franklin LimitedEDP RENEWABLES UK LIMITEDBattery storage5031 Oct 2025n/aAwaiting Consentsnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Richborough 11kVUK Power Networks0.9 km20 MW12 MW
Richborough Grid 33kVUK Power Networks1.3 km56 MW73 MW
Manston 11kVUK Power Networks6.4 km20 MW26 MW
Ramsgate 11kVUK Power Networks6.9 km25 MW2 MW
Betteshanger Grid 33kVUK Power Networks7.8 km64 MW24 MW
Betteshanger Local 11kVUK Power Networks7.8 km22 MW8.8 MW

Thinking of connecting near Richborough?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points