EAST KENT CONNECTION NODE B 132KV SUBSTATION: grid connection queue
EAST KENT CONNECTION NODE B 132KV SUBSTATION · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 228 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2036 to 31 Oct 2036.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Woodlands Farm BESS | SKY UK DEVELOPMENT LIMITED | Battery storage | 228 | 31 Oct 2036 | Low | 31 Oct 2036 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Chartham 11kV | UK Power Networks | 6.6 km | 10 MW | 5.2 MW |
| Canterbury Town 11kV | UK Power Networks | 9.6 km | 27 MW | 6.9 MW |
| Canterbury South 33kV | UK Power Networks | 10.2 km | 118 MW | 67 MW |
| Stanford 11kV | UK Power Networks | 10.3 km | 8.1 MW | 6.2 MW |
| Canterbury Local 11kV | UK Power Networks | 11.5 km | 24 MW | 3.5 MW |
| Lightweight Aggregates 11kV | UK Power Networks | 11.5 km | 1.7 MW | -0.6 MW |
Thinking of connecting near EAST KENT CONNECTION NODE B 132KV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- East Kent Connection Node B 400kV: 1,350 MW waiting
- Canterbury North 400kV: 57 MW waiting
- Sellindge 400kV: 576 MW waiting
- East Kent connection node A 400kV: 3,520 MW waiting
- Richborough 400kV: 249 MW waiting