Sellindge 400kV: grid connection queue
Sellindge 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 576 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Sellindge (Tertiary) | PIVOTED POWER LLP | Battery storage | 76 | 31 Oct 2028 | High | 31 Oct 2030 | Awaiting Consents | none |
| Partridge Farm BESS | Apatura Battery Ltd | Battery storage | 500 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Smeeth 11kV | UK Power Networks | 2.0 km | 1.1 MW | 2.2 MW |
| Sevington 11kV | UK Power Networks | 2.8 km | 16 MW | -5.2 MW |
| Sellindge Local 33kV | UK Power Networks | 3.8 km | 45 MW | 26 MW |
| Ashford East 11kV | UK Power Networks | 4.9 km | 8 MW | 3.1 MW |
| Ashford Central 6.6kV | UK Power Networks | 5.2 km | 31 MW | 2.6 MW |
| Singleton 6.6kV | UK Power Networks | 6.4 km | 20 MW | 11 MW |
Thinking of connecting near Sellindge 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- EAST KENT CONNECTION NODE B 132KV SUBSTATION: 228 MW waiting
- Canterbury North 400kV: 57 MW waiting
- East Kent Connection Node B 400kV: 1,350 MW waiting
- Dungeness 400kV: 1,000 MW waiting
- NORTH KENT CONNECTION NODE C 132KV SUBSTATION: 680 MW waiting