Sellindge 400kV: grid connection queue

Sellindge 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 576 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2037.

2projects in the queue
576 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
76 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Sellindge (Tertiary)PIVOTED POWER LLPBattery storage7631 Oct 2028High31 Oct 2030Awaiting Consentsnone
Partridge Farm BESSApatura Battery LtdBattery storage50031 Oct 2037Low31 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Smeeth 11kVUK Power Networks2.0 km1.1 MW2.2 MW
Sevington 11kVUK Power Networks2.8 km16 MW-5.2 MW
Sellindge Local 33kVUK Power Networks3.8 km45 MW26 MW
Ashford East 11kVUK Power Networks4.9 km8 MW3.1 MW
Ashford Central 6.6kVUK Power Networks5.2 km31 MW2.6 MW
Singleton 6.6kVUK Power Networks6.4 km20 MW11 MW

Thinking of connecting near Sellindge 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points