Benzene

NORTH KENT CONNECTION NODE C 132KV SUBSTATION: grid connection queue

NORTH KENT CONNECTION NODE C 132KV SUBSTATION · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 680 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.

2projects in the queue
680 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Upper College Farm BESSBluestone Energy LtdBattery storage48031 Oct 2037Low31 Oct 2037Scoping1
Manor Farm_SidcupFIRSTWAY SOLAR LTDBattery storage20031 Oct 2037Low31 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Sittingbourne Town 11kVUK Power Networks5.6 km23 MW4.6 MW
Sittingbourne West 11kVUK Power Networks6.2 km36 MW18 MW
Harrietsham 11kVUK Power Networks6.5 km14 MW5.1 MW
Sittingbourne Grid 33kVUK Power Networks7.1 km119 MW8.2 MW
Grovehurst Local 11kVUK Power Networks8.3 km22 MW5.3 MW
Faversham 11kVUK Power Networks11.4 km26 MW15 MW

Thinking of connecting near NORTH KENT CONNECTION NODE C 132KV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.