Benzene

Kemsley: grid connection queue

Kemsley GSP · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 100 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.

1project in the queue
100 MWwaiting to connect
36 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Barge Way 120MW BESSFPC ELECTRIC LAND LIMITEDBattery storage10031 Oct 2033Low31 Oct 2033Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Sittingbourne Town 11kVUK Power Networks2.8 km23 MW4.6 MW
Grovehurst Local 11kVUK Power Networks3.6 km22 MW5.3 MW
Sittingbourne West 11kVUK Power Networks5.4 km36 MW18 MW
Sittingbourne Grid 33kVUK Power Networks6.7 km119 MW8.2 MW
Eastchurch Prison 6.6kVUK Power Networks7.2 km5.9 MW3 MW
Minster 6.6kVUK Power Networks8.2 km8.3 MW4.4 MW

Thinking of connecting near Kemsley?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points