North Kent Connection Node C 400kV: grid connection queue

North Kent Connection Node C 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 532 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2038.

2projects in the queue
532 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Hurst BESSLuminous Energy Group LimitedBattery storage32031 Oct 2037Low31 Oct 2037Scoping1
Hurst BESSFIRSTWAY SOLAR LTDBattery storage21231 Oct 2038Low31 Oct 2038Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Grain 11kVUK Power Networks3.3 km12 MW3.9 MW
Kingsnorth Grid 11kVUK Power Networks5.1 km12 MW22 MW
Queenborough 6.6kVUK Power Networks5.5 km16 MW13 MW
Sheerness 6.6kVUK Power Networks5.9 km17 MW7.2 MW
Sheerness Grid 33kVUK Power Networks6.0 km23 MW30 MW
Grovehurst Local 11kVUK Power Networks8.3 km22 MW5.3 MW

Thinking of connecting near North Kent Connection Node C 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.