East Kent Connection Node B 400kV: grid connection queue

East Kent Connection Node B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 1,350 MW are waiting to connect here (largest by capacity: solar + storage, mixed and other). Contracted dates run from 31 Oct 2030 to 31 Oct 2036.

2projects in the queue
1,350 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Canterbury NorthCanterbury North 10 Renewables LimitedSolar + storage1,00031 Oct 2030Medium31 Oct 2030Scoping1
Project InvictaPROJECT INVICTA LIMITEDMixed and other35031 Oct 2036Low31 Oct 2036Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Canterbury Town 11kVUK Power Networks1.6 km27 MW6.9 MW
Canterbury South 33kVUK Power Networks1.9 km118 MW67 MW
Canterbury Local 11kVUK Power Networks2.1 km24 MW3.5 MW
Chartham 11kVUK Power Networks6.3 km10 MW5.2 MW
Wingham 11kVUK Power Networks8.1 km24 MW7.1 MW
Herne Bay 11kVUK Power Networks8.4 km-42.2 MW25 MW

Thinking of connecting near East Kent Connection Node B 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.