Benzene

East Kent connection node A 400kV: grid connection queue

East Kent connection node A 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

7 projects with 3,520 MW are waiting to connect here (largest by capacity: solar + storage, mixed and other). Contracted dates run from 31 Oct 2033 to 31 Oct 2037.

7projects in the queue
3,520 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Sellindge WestSellindge West 10 Renewables LimitedSolar + storage1,00031 Oct 2033Low31 Oct 2033Scoping1
Dungeness Energy Park (Dungeness 400kV)SOUTH KENT ENERGY PARK LIMITEDSolar + storage50031 Oct 2033Low31 Oct 2033Scopingnone
GF SELLINDGE BESSGF Sellindge Energy LtdBattery storage30031 Oct 2036Low31 Oct 2036Scoping1
Newchurch High Impact Energy HubTELIS ENERGY UK LIMITEDMixed and other1,00031 Oct 2037Low31 Oct 2037Scoping1
Fairmead and Yewtree FarmQAIR RENEWABLES UK LIMITEDBattery storage24031 Oct 2037Low31 Oct 2037Scoping1
Henley Downs Farm BESSNINFIELD BESS LTDBattery storage24031 Oct 2037Low31 Oct 2037Scoping1
Lightsource Newchurch PV/BESSLightsource Renewable UK Development LimitedSolar + storage24031 Oct 2037Low31 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Faversham 11kVUK Power Networks4.6 km26 MW15 MW
Whitstable 11kVUK Power Networks4.9 km-40.9 MW12 MW
Chartham 11kVUK Power Networks8.8 km10 MW5.2 MW
Leysdown 6.6kVUK Power Networks8.9 km1.6 MW0.2 MW
Canterbury South 33kVUK Power Networks9.0 km118 MW67 MW
Herne Bay 11kVUK Power Networks9.0 km-42.2 MW25 MW

Thinking of connecting near East Kent connection node A 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points