Littlebrook 400kV: grid connection queue

Littlebrook 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 57 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 17 Oct 2029 to 17 Oct 2029.

1project in the queue
57 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
ER LBR EnergyER PROJECT DEVELOPMENT CO LIMITEDSolar + storage5717 Oct 2029Medium17 Oct 2029Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Littlebrook Park 11kVUK Power Networks0.5 km92 MW48 MW
Crossways 11KVUK Power Networks1.0 km19 MW13 MW
Stone 11kVUK Power Networks1.9 km1.6 MW8.3 MW
Stonemarshes 11kVUK Power Networks2.0 km34 MW8.8 MW
Purfleet Grid 33kVUK Power Networks2.3 km104 MW24 MW
Dartford Grid B 11kVUK Power Networks2.4 km58 MW14 MW

Thinking of connecting near Littlebrook 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points