Littlebrook 132kV: grid connection queue
Littlebrook 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 550 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 15 Oct 2027 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Littlebrook BESS | ECODEV (SOUTH) LTD | Battery storage | 300 | 15 Oct 2027 | High | 14 Oct 2029 | Awaiting Consents | 2 |
| Low Carbon Energy Centre BESS Joyce Green Lane | NET ZERO MARINE SERVICES LIMITED | Battery storage | 250 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 18 Aug 2026 | Littlebrook BESS | 15 Jul 2027 | 15 Oct 2027 | +3 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Littlebrook Park 11kV | UK Power Networks | 0.8 km | 92 MW | 48 MW |
| Crossways 11KV | UK Power Networks | 0.9 km | 19 MW | 13 MW |
| Stonemarshes 11kV | UK Power Networks | 1.8 km | 34 MW | 8.8 MW |
| Stone 11kV | UK Power Networks | 1.9 km | 1.6 MW | 8.3 MW |
| Purfleet Grid 33kV | UK Power Networks | 2.1 km | 104 MW | 24 MW |
| Purfleet Primary 11kV T1 & T2 | UK Power Networks | 2.3 km | 20 MW | 7.7 MW |
Thinking of connecting near Littlebrook 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Littlebrook 400kV: 57 MW waiting
- NorthFleet 400kV: 300 MW waiting
- Barking West: 100 MW waiting
- Hurst 275kV: 228 MW waiting
- London North East Connection Node A 132kv: 200 MW waiting