Learlielaw Energy Storage 132kV: grid connection queue
Learlielaw Energy Storage 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 100 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Learielaw Energy Storage | Learielaw Energy Storage Limited | Battery storage | 100 | 31 Oct 2028 | High | 31 Oct 2030 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| East Mains | SP Energy Networks | 1.4 km | 14 MW | 17 MW |
| Broxburn | SP Energy Networks | 1.8 km | 16 MW | |
| Newbridge | SP Energy Networks | 2.9 km | 27 MW | 12 MW |
| Cameron | SP Energy Networks | 3.4 km | 5.4 MW | |
| Carron | SP Energy Networks | 3.4 km | 26 MW | 14 MW |
| Cousland | SP Energy Networks | 4.4 km | 12 MW |
Thinking of connecting near Learlielaw Energy Storage 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Currie 275/132kV: 150 MW waiting
- Harburn 400kV: 250 MW waiting
- Harburn 132/33kV Grid Supply Point: 43 MW waiting
- Inverkeithing: 50 MW waiting
- Inverkeithing 132/33kV: 42 MW waiting