Harburn 132/33kV Grid Supply Point Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 43 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 29 Oct 2032 to 29 Oct 2032.

1project in the queue
43 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Gladsmuir Wind FarmWIND ESTATE (UK) LIMITEDOnshore wind4329 Oct 2032Low29 Oct 2032Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
West CalderSP Energy Networks5.8 km12 MW2.8 MW
DedridgeSP Energy Networks7.1 km16 MW
AlmondvaleSP Energy Networks7.2 km27 MW13 MW
KirktonSP Energy Networks8.2 km14 MW
CouslandSP Energy Networks9.0 km12 MW
BlackburnSP Energy Networks10.2 km12 MW4.2 MW

Thinking of connecting near Harburn 132/33kV Grid Supply Point?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points