Whitburn 400kV substation: grid connection queue

Whitburn 400kV substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 280 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2030 to 31 Oct 2030.

1project in the queue
280 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Alcemi Armadale BESSALCEMI STORAGE DEVELOPMENTS 8 LTDBattery storage28031 Oct 2030Medium31 Oct 2030Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
PaulvilleSP Energy Networks1.3 km26 MW12 MW
BlackburnSP Energy Networks1.9 km12 MW4.2 MW
ArmadaleSP Energy Networks2.5 km-10.5 MW12 MW
PyramidSP Energy Networks3.0 km26 MW17 MW
PolkemmetSP Energy Networks4.3 km11 MW
DeansSP Energy Networks5.7 km7.1 MW

Thinking of connecting near Whitburn 400kV substation?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points