Newarthill 275 kV: grid connection queue
Newarthill 275 kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 400 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Apr 2035 to 30 Apr 2035.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Motherwell 400MW BESS (Formerly Castlehill BESS) | SPV GPC 3 Ltd | Battery storage | 400 | 30 Apr 2035 | Low | 30 Apr 2035 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Shotts | SP Energy Networks | 1.3 km | 13 MW | |
| Allanbank | SP Energy Networks | 3.7 km | 26 MW | 17 MW |
| Forth | SP Energy Networks | 7.3 km | 1.6 MW | 16 MW |
| Polkemmet | SP Energy Networks | 7.4 km | 11 MW | |
| Newhouse | SP Energy Networks | 9.5 km | 22 MW | 5.5 MW |
| Belhaven West | SP Energy Networks | 9.8 km | 24 MW | 11 MW |
Thinking of connecting near Newarthill 275 kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Heathland 132/33kV: 80 MW waiting
- North Lanrigg: 200 MW waiting
- Newarthill Energy Park 275kV: 300 MW waiting
- Armadale 132kV: 60 MW waiting
- Whitburn 400kV substation: 280 MW waiting