Newarthill Energy Park 275kV: grid connection queue
Newarthill Energy Park 275kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 300 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2029 to 31 Oct 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Newarthill Energy Park | Dalzell (Newarthill) Ltd | Battery storage | 300 | 31 Oct 2029 | Medium | 31 Oct 2029 | Awaiting Consents | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 7 Jul 2026 | Newarthill Energy Park | 28 Oct 2027 | 28 Oct 2029 | +24 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Newhouse | SP Energy Networks | 0.9 km | 22 MW | 5.5 MW |
| Chapelhall | SP Energy Networks | 1.1 km | 25 MW | 20 MW |
| Coddington Cres | SP Energy Networks | 2.0 km | 26 MW | 15 MW |
| Carfin | SP Energy Networks | 2.6 km | 24 MW | 10 MW |
| Towers Road | SP Energy Networks | 4.9 km | 28 MW | 8.8 MW |
| Bellshill (Primary) | SP Energy Networks | 4.9 km | 23 MW | 11 MW |
Thinking of connecting near Newarthill Energy Park 275kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- North Lanrigg: 200 MW waiting
- Coatbridge: 60 MW waiting
- Newarthill 275 kV: 400 MW waiting
- Strathaven 400kV: 800 MW waiting
- Strathaven 400/275kV: 500 MW waiting