Harburn 400kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 250 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| West Caulder BESS | GPC Project 13 Ltd | Battery storage | 250 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| West Calder | SP Energy Networks | 5.8 km | 12 MW | 2.8 MW |
| Dedridge | SP Energy Networks | 7.1 km | 16 MW | |
| Almondvale | SP Energy Networks | 7.2 km | 27 MW | 13 MW |
| Kirkton | SP Energy Networks | 8.2 km | 14 MW | |
| Cousland | SP Energy Networks | 9.0 km | 12 MW | |
| Blackburn | SP Energy Networks | 10.2 km | 12 MW | 4.2 MW |
Thinking of connecting near Harburn 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Harburn 132/33kV Grid Supply Point: 43 MW waiting
- Heathland 132/33kV: 80 MW waiting
- Whitburn 400kV substation: 280 MW waiting
- Learlielaw Energy Storage 132kV: 100 MW waiting
- Armadale 132kV: 60 MW waiting