Currie 275/132kV: grid connection queue
Currie 275/132kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 150 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 13 Apr 2029 to 13 Apr 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Riccarton | M2 Energy Storage Limited | Solar + storage | 150 | 13 Apr 2029 | Medium | 13 Apr 2029 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Currie | SP Energy Networks | 1.6 km | 33 MW | 18 MW |
| Colinton North | SP Energy Networks | 3.3 km | 14 MW | |
| Sighthill Farm | SP Energy Networks | 4.2 km | 28 MW | 6.8 MW |
| Kingsknowe Road North | SP Energy Networks | 5.2 km | 13 MW | |
| South Gyle | SP Energy Networks | 5.3 km | 13 MW | |
| Oxgangs Road | SP Energy Networks | 5.5 km | 10 MW |
Thinking of connecting near Currie 275/132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Whitehouse 275kV: 249 MW waiting
- Dunlaw Extension 132/33kV: 53 MW waiting
- Learlielaw Energy Storage 132kV: 100 MW waiting
- SHAWFAIR 400KV SUBSTATION: 240 MW waiting
- Harburn 400kV: 250 MW waiting