Whitehouse 275kV: grid connection queue

Whitehouse 275kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 249 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2034 to 31 Oct 2034.

1project in the queue
249 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Whitehouse BESS stationIGP INTERNATIONAL PROSPECTING LIMITEDBattery storage24931 Oct 2034Low31 Oct 2034Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026Whitehouse BESS station31 Jul 203231 Oct 2034+27 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
MortonhallSP Energy Networks1.0 km16 MW
Maxwell StreetSP Energy Networks1.0 km27 MW11 MW
Oxgangs RoadSP Energy Networks1.9 km10 MW
Kings BuildingsSP Energy Networks2.1 km12 MW
S&N Breweries ViewforthSP Energy Networks2.7 km14 MW
Martin MillerSP Energy Networks2.9 km26 MW17 MW

Thinking of connecting near Whitehouse 275kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points