Dalkeith 400kV: grid connection queue
Dalkeith 400kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
3 projects with 600 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Jun 2031 to 31 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Carberry BESS (was Smeaton BESS) | HARMONY CBR LTD | Battery storage | 200 | 30 Jun 2031 | Medium | 30 Jun 2031 | Scoping | 1 |
| Whitecraig BESS | Apatura Battery Ltd | Battery storage | 200 | 30 Jun 2031 | Medium | 30 Jun 2031 | Scoping | 1 |
| Salters Battery Storage | BUCCLEUCH ESTATES, LTD. (THE) | Battery storage | 200 | 31 Oct 2031 | Medium | 31 Oct 2031 | Awaiting Consents | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Lugton | SP Energy Networks | 1.2 km | 6.8 MW | |
| Lady Victoria | SP Energy Networks | 3.6 km | 17 MW | 5.3 MW |
| Monktonhall | SP Energy Networks | 4.1 km | 27 MW | 8.8 MW |
| Poltonhall | SP Energy Networks | 4.7 km | 10 MW | 3 MW |
| Niddrie | SP Energy Networks | 5.5 km | 10 MW | 9.4 MW |
| Little France | SP Energy Networks | 5.7 km | 27 MW | 14 MW |
Thinking of connecting near Dalkeith 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- SHAWFAIR 400KV SUBSTATION: 240 MW waiting
- Dunlaw Extension 132/33kV: 53 MW waiting
- Whitehouse 275kV: 249 MW waiting
- Meadowmill 400/132kV: 342 MW waiting
- Torfichen Energy Park 132kV: 150 MW waiting