Meadowmill 400/132kV: grid connection queue
Meadowmill 400/132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 342 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Jul 2027 to 31 Jul 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Gresham House Cockenzie BESS | COCKENZIE STORAGE LIMITED | Battery storage | 240 | 31 Jul 2027 | High | 30 Jul 2029 | Under Construction/Commissioning | 2 |
| Cockenzie BESS | COCKENZIE STORAGE B LTD | Battery storage | 102 | 31 Jul 2027 | High | 30 Jul 2029 | Under Construction/Commissioning | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 7 Jul 2026 | Cockenzie BESS | 31 Jul 2026 | 31 Jul 2027 | +12 months |
| 23 Jun 2026 | Gresham House Cockenzie BESS | 31 Jul 2026 | 31 Jul 2027 | +12 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Prestonpans | SP Energy Networks | 0.3 km | 26 MW | 13 MW |
| Tranent | SP Energy Networks | 2.6 km | 28 MW | 3.9 MW |
| Monktonhall | SP Energy Networks | 7.3 km | 27 MW | 8.8 MW |
| Pencaitland | SP Energy Networks | 7.5 km | 9 MW | 11 MW |
| Niddrie | SP Energy Networks | 10.3 km | 10 MW | 9.4 MW |
| Lugton | SP Energy Networks | 10.5 km | 6.8 MW |
Thinking of connecting near Meadowmill 400/132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Cockenzie 400/275kV: 1,340 MW waiting
- Cockenzie 275kV substation: 540 MW waiting
- Cockenzie 275/33kV: 63 MW waiting
- Dalkeith 400kV: 600 MW waiting
- SHAWFAIR 400KV SUBSTATION: 240 MW waiting