Cockenzie 275/33kV: grid connection queue
Cockenzie 275/33kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 63 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2028 to 31 Oct 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Dolphingstone Farm | BSSL EAST LOTHIAN 1 LTD | Battery storage | 63 | 31 Oct 2028 | High | 31 Oct 2030 | Consents Approved | 2 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Pencaitland | SP Energy Networks | 3.8 km | 9 MW | 11 MW |
| Peppercraigs | SP Energy Networks | 6.4 km | 15 MW | 12 MW |
| Tranent | SP Energy Networks | 8.6 km | 28 MW | 3.9 MW |
| Prestonpans | SP Energy Networks | 9.7 km | 26 MW | 13 MW |
| East Linton | SP Energy Networks | 13.5 km | 2.2 MW | |
| Monktonhall | SP Energy Networks | 13.8 km | 27 MW | 8.8 MW |
Thinking of connecting near Cockenzie 275/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Cockenzie 400/275kV: 1,340 MW waiting
- Cockenzie 275kV substation: 540 MW waiting
- Meadowmill 400/132kV: 342 MW waiting
- Fallago 400/33kV: 150 MW waiting
- Newlands Hill 132/33kV: 119 MW waiting