Fallago 400/33kV: grid connection queue

Fallago 400/33kV · SP Transmission (southern Scotland) · register of 26 November 2026

2 projects with 150 MW are waiting to connect here (largest by capacity: onshore wind, battery storage). Contracted dates run from 30 Apr 2029 to 30 Apr 2033.

2projects in the queue
150 MWwaiting to connect
144 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
100 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Dunside Wind Farm (Formally Fallago Rig 2 Wind Farm)EDF ENERGY RENEWABLES LIMITEDOnshore wind10030 Apr 2029High17 Mar 2031Awaiting Consentsnone
Shielburn Energy ParkSUNLAWS DEVELOPMENT COMPANY LIMITEDBattery storage5030 Apr 2033Low30 Apr 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
LauderSP Energy Networks13.4 km4.7 MW
WhitchesterSP Energy Networks14.4 km3.9 MW
PeppercraigsSP Energy Networks15.8 km15 MW12 MW
PencaitlandSP Energy Networks16.0 km9 MW11 MW
East LintonSP Energy Networks17.0 km2.2 MW
GordonSP Energy Networks18.3 km3.1 MW

Thinking of connecting near Fallago 400/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.