Borders Connection Node A 400kV: grid connection queue

Borders Connection Node A 400kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 240 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2035 to 30 Oct 2035.

1project in the queue
240 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Middle Farm ChollertonENRAY POWER LTDSolar + storage24030 Oct 2035Low30 Oct 2035Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
LauderSP Energy Networks5.4 km4.7 MW
Glendinning TerraceSP Energy Networks14.1 km2.1 MW
Earlston (Borders)SP Energy Networks16.0 km1.6 MW
NetherdaleSP Energy Networks16.3 km27 MW9.3 MW
PencaitlandSP Energy Networks18.1 km9 MW11 MW
GordonSP Energy Networks18.5 km3.1 MW

Thinking of connecting near Borders Connection Node A 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.