Torfichen Energy Park 132kV: grid connection queue

Torfichen Energy Park 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 150 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2030 to 31 Oct 2030.

1project in the queue
150 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
150 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Torfichen Energy ParkTorfichen Energy LimitedOnshore wind + storage15031 Oct 2030High16 Sep 2032Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Lady VictoriaSP Energy Networks9.5 km17 MW5.3 MW
LoanstoneSP Energy Networks10.7 km8.2 MW6.3 MW
PoltonhallSP Energy Networks11.6 km10 MW3 MW
PenicuikSP Energy Networks12.0 km12 MW3.7 MW
Bush EstateSP Energy Networks12.4 km11 MW16 MW
BurghleeSP Energy Networks12.9 km6.1 MW

Thinking of connecting near Torfichen Energy Park 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points