Kaimes: grid connection queue

Kaimes GSP · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 51 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Apr 2027 to 30 Apr 2027.

1project in the queue
51 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
51 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Kaimes Energy ParkHP Trotter t/a Printonan FarmBattery storage5130 Apr 2027High29 Apr 2029Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
West LintonSP Energy Networks7.0 km11 MW5.4 MW
KingslandSP Energy Networks8.4 km12 MW0.9 MW
LoanstoneSP Energy Networks11.1 km8.2 MW6.3 MW
PenicuikSP Energy Networks11.8 km12 MW3.7 MW
Bush EstateSP Energy Networks14.6 km11 MW16 MW
BurghleeSP Energy Networks16.6 km6.1 MW

Thinking of connecting near Kaimes?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points