Gala North 400/132kV: grid connection queue

Gala North 400/132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

3 projects with 314 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2030 to 30 Apr 2033.

3projects in the queue
314 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Lightsource ThreepwoodLightsource Renewable UK Development LimitedBattery storage15031 Oct 2030Medium31 Oct 2030Scoping1
Scawd Law Wind FarmFRED OLSEN RENEWABLES LIMITEDOnshore wind + storage6430 Apr 2032Low30 Apr 2032Scoping1
Woodheads Energy ParkABO ENERGY UNITED KINGDOM LTDSolar + storage10030 Apr 2033Low30 Apr 2033Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
KingslandSP Energy Networks11.5 km12 MW0.9 MW
Glendinning TerraceSP Energy Networks12.4 km2.1 MW
Yair BridgeSP Energy Networks13.1 km5.2 MW
NetherdaleSP Energy Networks15.1 km27 MW9.3 MW
SelkirkSP Energy Networks15.3 km11 MW4.5 MW
LauderSP Energy Networks17.4 km4.7 MW

Thinking of connecting near Gala North 400/132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.