Gala North 400/132kV: grid connection queue
Gala North 400/132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
3 projects with 314 MW are waiting to connect here (largest by capacity: battery storage, solar + storage). Contracted dates run from 31 Oct 2030 to 30 Apr 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Lightsource Threepwood | Lightsource Renewable UK Development Limited | Battery storage | 150 | 31 Oct 2030 | Medium | 31 Oct 2030 | Scoping | 1 |
| Scawd Law Wind Farm | FRED OLSEN RENEWABLES LIMITED | Onshore wind + storage | 64 | 30 Apr 2032 | Low | 30 Apr 2032 | Scoping | 1 |
| Woodheads Energy Park | ABO ENERGY UNITED KINGDOM LTD | Solar + storage | 100 | 30 Apr 2033 | Low | 30 Apr 2033 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Kingsland | SP Energy Networks | 11.5 km | 12 MW | 0.9 MW |
| Glendinning Terrace | SP Energy Networks | 12.4 km | 2.1 MW | |
| Yair Bridge | SP Energy Networks | 13.1 km | 5.2 MW | |
| Netherdale | SP Energy Networks | 15.1 km | 27 MW | 9.3 MW |
| Selkirk | SP Energy Networks | 15.3 km | 11 MW | 4.5 MW |
| Lauder | SP Energy Networks | 17.4 km | 4.7 MW |
Thinking of connecting near Gala North 400/132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Galashiels 132/33kV: 73 MW waiting
- GALA NORTH 132KV SUBSTATION: 67 MW waiting
- Torfichen Energy Park 132kV: 150 MW waiting
- Borders Connection Node A 400kV: 240 MW waiting
- Kaimes: 51 MW waiting