SHAWFAIR 400KV SUBSTATION: grid connection queue

SHAWFAIR 400KV SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 240 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Apr 2034 to 30 Apr 2034.

1project in the queue
240 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Burdiehouse BESSIBV Burdiehouse Energy Park LimitedBattery storage24030 Apr 2034Low30 Apr 2034Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
LugtonSP Energy Networks2.0 km6.8 MW
Little FranceSP Energy Networks2.6 km27 MW14 MW
NiddrieSP Energy Networks2.9 km10 MW9.4 MW
PoltonhallSP Energy Networks3.6 km10 MW3 MW
MonktonhallSP Energy Networks3.7 km27 MW8.8 MW
Frogston Road EastSP Energy Networks4.3 km14 MW14 MW

Thinking of connecting near SHAWFAIR 400KV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points