Dunlaw Extension 132/33kV: grid connection queue
Dunlaw Extension 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 53 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Ditcher Law | E Power Limited | Onshore wind + storage | 53 | 31 Oct 2031 | High | 16 Sep 2033 | Awaiting Consents | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Frogston Road East | SP Energy Networks | 1.1 km | 14 MW | 14 MW |
| Little France | SP Energy Networks | 1.8 km | 27 MW | 14 MW |
| Kings Buildings | SP Energy Networks | 1.8 km | 12 MW | |
| Mortonhall | SP Energy Networks | 3.4 km | 16 MW | |
| Niddrie | SP Energy Networks | 3.7 km | 10 MW | 9.4 MW |
| Burghlee | SP Energy Networks | 3.8 km | 6.1 MW |
Thinking of connecting near Dunlaw Extension 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Whitehouse 275kV: 249 MW waiting
- SHAWFAIR 400KV SUBSTATION: 240 MW waiting
- Dalkeith 400kV: 600 MW waiting
- Currie 275/132kV: 150 MW waiting
- Meadowmill 400/132kV: 342 MW waiting